Air-bend tonnage calculator
Force per metre for an air bend, and the press rating it demands.
Base P = (1.42 × 450 × 3²) / 24 = 240 kN/m
Method (Air bend) × 1 × 1 m
Required = 240 kN = 24 tonne
Die at 80 % rating needs a press of 31 tonne
Air-bend figures in mild steel unless stated. Nominal thickness; measure the coil. Values are a starting point — press rating, die condition, material certificate and grain direction move the real number.
Have the actual STEP file measured against these limits — first part freeThe rule
P (kN/m) = (1.42 × S × T²) / V, with S = tensile strength in MPa. Never run past 80 % of the press rating.
Tonnage is what decides whether the press can make the part at all. It is set by thickness and die opening, not by effort.
What breaks when this is ignored
- Choosing a die narrow enough to look right and overloading the press — tonnage scales with 1 / V.
- Off-centre loading, which twists the ram long before the press reaches its rating.
- Punch tip load ignored: a sharp punch mushrooms in stock it was never sized for.
- Coining quoted at air-bend tonnage. Coining is 5–8×.
Typical die opening by thickness
| Thickness | Minimum V | Typical V | Maximum V |
|---|---|---|---|
| 0.5 – 1.2 mm | 6 T | 8 T | 10 T |
| 1.3 – 3.0 mm | 8 T | 8 T | 10 T |
| 3.1 – 6.0 mm | 8 T | 10 T | 12 T |
| 6.1 – 12 mm | 10 T | 12 T | 16 T |
Notes from the floor
- Method factor applied on top of the material figure: air 1×, bottoming 2–3×, coining 5–8×.
- V ≈ 8 × T is the everyday starting point. Inside radius of an air bend comes out around 0.16 × V.